Contract & RFP Guidelines
System Administration's Requests for Proposals (RFPs) must be done for procurements greater than $125,000. They may also be done for lower dollar value procurements but are not required. The general purpose of the procurement process is to ensure that contract awards are made in the best interest of the State and in furtherance of the State University's mission. The following outlines the RFP process at System Administration and the roles and responsibilities of all individuals involved in the process.
The Project Manager is the department designee responsible for managing the procurement. The Contract Unit Officer is the Contract Unit staff in the Business Office designated to assist and guide the department through the entire procurement process.
Review the RFP Procedures
Contracts involving RFP:
| Description | Time | Approximate Time Frame |
| Meet with Contract Unit Staff to discuss needs and funding |
1 week |
8-10 months prior to start date |
| Develop the RFP and bidders list |
1 month |
8 months prior to start date |
| Contract Unit staff and Legal staff review of RFP |
2-3 weeks |
7 months prior to start date |
| Advertise, then release RFP |
1 week |
7 months prior to start date |
| Develop Evaluation Criteria & select evaluation team members (this must be completed before proposals are opened) |
1-2 weeks |
7 months prior to start date |
| Wait for, Receive and Evaluate Proposals |
3-6 weeks |
6 months prior to start date |
| Vendor Demonstrations if required |
1 week |
6 months prior to start date |
| Award and Negotiate contract terms |
4 weeks |
5 months prior to start date |
| Legal review by all parties |
1-2 weeks |
4 months prior to start date |
| Finalize contract documents, required signatures, finalize procurement record |
1-2 weeks |
3 months prior to start date |
| Submit the contract to A/G and OSC |
5-7 weeks |
3 months prior to start date |
Contract Renewals:
| Description | Time | Approximate Time Frame |
| Contact Vendor |
1-2 days |
8-10 months prior to renewal date |
| Negotiate any changes in contract terms & conditions |
4 weeks |
6 months prior to renewal date |
| Revise contract document |
1-2 weeks |
5 months prior to renewal date |
| Legal review by all parties |
1-2 weeks |
4 months prior to renewal date |
| Finalize contract documents, required signatures, finalize procurement record |
1-2 weeks |
3 months prior to renewal date |
| Submit the contract to A/G and OSC |
5-7 weeks |
3 months prior to start date |
Contracting Process and Approximate Timeline involving RFPs
| Description | Approximate Time |
| 1. Need for a university-wide contract is identified and funding is ensured |
|
| 2. Advisory group is formed (campus representative, stakeholders, users) |
1 week |
| 3. Subcommittee of advisory group identified to write project specifications |
1 week |
| 4. Subcommittee develops the RFP, evaluation methodology and identifies the bidders list |
1-2 months |
| 5. System Administration contract staff reviews and formalizes RFP and the evaluation methodology (proposals cannot be opened until methodology is finalized). |
2 weeks |
| 6. SUNY counsel reviews the RFP |
1 week |
| 7. Place ad in NYS Contract Reporter and release the RFP, and select evaluation team from advisory groups. Ad must appear for three weeks. |
3 weeks |
| 8. Receive and Evaluate Proposals |
2 weeks |
| 9. Vendor Demonstrations if required |
1 week |
| 10. Contract Unit reviews and performs final compilation of evaluation score sheets and makes award in consultation with the project manager. |
1 week |
| 11. Project manager negotiates contract terms & conditions |
2 weeks |
| 12. Contract Unit finalizes contract documents, SUNY counsel reviews, and documents sent to vendor for signature |
1-2 weeks |
| 13. Vendor returns contract documents, SUNY signs contracts, procurement record is finalized |
1 week |
| 14. Submit the contract to AG and OSC for approval |
6-8 weeks |